During four days at the end of February skilled pipeline
technicians made a major, unique repair to the main natural gas transmission
line that serves all of Newport.
The repair to the main line traveling underground through
White Pine required replacement of a 42-foot section of steel pipe but gas flow
could not be stopped.
Jefferson-Cocke County Utility District Manager Tommy
Bible said it was a critical operation with a certain amount of danger and high
cost.
Few customers except those along Pratt Drive in White
Pine were even aware it took place. Natural gas continued flowing from Feb.
22-25, because a bypass pipe was in place while the 50-plus year old pipeline
section was replaced.
Bible said, "I have only the highest praise for our
utility workers and the White Pine contractor, Barnard,." Barnard EMC is a
specialist doing this hazardous, and important repair. They used seldom seen
giant valves called Mueller valves to accomplish the work.
"We couldn't shut it down. It would take days to get
the system back up," he said, explaining why the repair had to be done
without stop the high-pressure flow. That was another danger-pipeline pressures
that range from 400 to 700 pounds per square inch. Compare that to the
half-pound pressure of gas flowing to residences.
It was no surprise to Jefferson-Cocke County Utility
District (JCCUD) technicians and management that the work would have to be
done, but it fell at wintertime because a known small leak began getting worse.
The miles-long pipeline originating near I-81 is a
lateral off East Tennessee Natural Gas Company's major feed to upper East Tenn.
The local line was placed in 1958 shortly after the gas district was founded.
Unfortunately and not known by many people, one of the
pipeline workers who happened to live in White Pine decided he would tap into
the line. Bible said this is something that just should never be permitted.
It went unobserved for decades until recent years that
during routine checks for gas leaks discovered it. They abandoned the old
service line and placed a proper tap to the home. Technicians monitored the
pipeline leak, which began getting worse this winter. The JCCUD commission approved
the expensive repair-the final bill will be about $30,000.
Barnard employees first dug a trench and used valves to
shunt the gas while making repairs. The high-pressure flow, feeding thousands
of customers and 70 percent of the total industrial load, dropped the
temperature so much on the welds that the pipe sustained hairline fractures.
Engineers recommended digging a longer trench and
replacing a 42-feet section. Hugh Mueller valves weighing hundreds of pounds
are used temporarily to clamp onto the existing pipe. Then a boring head is
attached to the top of the valve and large holes are cut into the pipe.
This is all done while gas continues to flow. At the same
time, a section of four-inch pipe is put in place several feet above the
six-inch line. Then the valve allows workers to divert the gas flow from the
large pipe through the four-inch pipe.
Once this happened, they cut out the six-inch pipe,
lifted it out, and lowered a new section that was welded into place. Highly
skilled welders from Cookeville came in to do the job.
Bible said when they made the weld, co-workers used a
propane torch to heat the pipeline before and after welding. This allowed the
large pipe to cool slowly and prevent cracking.
Once the new section was in place, the upper four-inch
bypass was disconnected, Mueller valves taken off, and the pipe covered with
earth-with expectations not to have to see it again for another 50 years.
"We were fortunate these skilled technicians were
right here in White Pine. Everything went extremely well and it was not an easy
thing to do. Everyone did an outstanding job," said Bible.
Inspectors dug up sections of the main pipeline years ago
to check its integrity. Bible said he was pleased to find out that it was in
extremely good, sound condition after 52 years. One thing that prevents
corrosion is a small electric current always running through the pipe that
thwarts the break down of the metal.
Several years ago JCCUD began a multi-phase project to
build a second transmission line. Several phases have been completed, the last
phases, which would require placing pipe under Douglas Lake, would cost more
than $4 million.
Bible said eventually this might have to be done but it
would be a dead cost to rate payers because it would not add customers to defray
the cost. So it may still be on hold for a few more years.